Galaxycore 12-inch BSI Facility to Start Production in 2 Years

Laoyaoba: Galaxycore says on the investor interaction platform that the company's 12-inch CIS BSI facility construction is progressing smoothly, and the main building has been capped on August 16. The company expects to start the production in 2 years. The fab capacity is 20,000 wafers per month.

In 2018, 2019 and 2020, the gross profit margin of Galaxycore's CMOS sensors was 25.32%, 27.50% and 28.54%, respectively which is similar to or even higher than that of its competitors. Galaxycore is confident in the competitiveness of its new high-end products in development now.